Major projects
We are working on a 30 year programme to replace all the metallic pipes within 30m of property with new polyethylene (PE) pipes. These PE pipes are more flexible and robust and if left undisturbed will last for decades, ensuring the continued benefits of gas for years to come.
As a consequence of our renewal programme you may be affected by our works. Modern methods of pipe laying mean that we can often use techniques that allow us not to dig up lengthy stretches of the highway and can even insert the new pipes inside the old ones.
We pride ourselves in the work we do and will always strive to minimise the inconvenience caused by keeping our customers informed and by working closely with local authorities, police and transport companies when planning our projects.
- Arundel, High Street area07/10/2009We have now begun work to replace ageing gas mains and services in the High Street area of Arundel.
- Beckenham High Street27/07/2010We are currently carrying out work on a £180,000 project to renew the gas supply network in Beckenham.
- Blackfen23/07/2010We are currently carrying out work to upgrade the gas supply network in Blackfen.
- Bladindon Drive, Bexley21/05/2010Work is being carried out on a £320,000 project to renew the gas main network in Bexley.
- Bournemouth, Poole Road17/08/2010Work is progressing on a £500,000 project to renew the gas main network in Bournemouth.
- Brighton, St James Street17/02/2010We are currently carrying out work on a £70,000 project to renew the gas supply network in central Brighton.
- Byfleet, High Road29/05/2009A 38 week project to renew gas mains in Byfleet begins on 8 June
- Cardross to Helensburgh update01/07/2010This project is now entering its 13th week and Morgan Sindall, the contractor working on SGN's behalf, has constructed approximately 3.1km of the new pipeline and excavated approximately 4km of ground. We would like to thank local residents and road users for their continued patience and understanding while these essential engineering works are carried out.
- Cheam, West Drive and Rugby Lane16/07/2010We will shortly be carrying out essential work on a project to renew the gas main network in Cheam.
- Cholsey, Papist Way08/02/2010Work will soon get underway on a £220,000 project to upgrade the gas main network in Cholsey.
- Cobham - Weybridge, Seven Hills Road04/01/2010Work is progressing on a £3 million project to reinforce and renew the gas network in Seven Hills Road between Cobham and Weybridge/Walton on Thames.
- Cross - Solent, Gas pipeline replacement25/02/2010A £20 million project to replace the gas mains under The Solent between the mainland and the Isle of Wight begins this summer.
- Edinburgh, Belford Road06/09/2010Starting on Monday 18 October we will be carrying out a £51,000 project to replace the gas mains in Belford Road, Edinburgh.
- Edinburgh, Craigmount area06/09/2010A £584,000 project to renew the gas mains in the Craigmount area of Edinburgh is underway.
- Edinburgh, Drum Brae Drive06/09/2010Starting on Monday 20 September we will be carrying out a £561,000 project to renew the gas mains in the Drum Brae Drive area.
- Edinburgh, London Road22/07/2010The final stage of a £350,000 project to renew gas mains in London Road gets underway on Monday 26 July for four weeks.
- Ewell, London Road19/08/2010We are undertaking a £120,000 project to renew the gas mains in Ewell
- Farnham leaflet23/08/2010
- Farnham, Station Hill23/08/2010We will shortly be starting work on a £100,000 project to replace gas mains in Farnham.
- Faversham, West Street26/03/2009A £175,000 project to replace gas mains in Faversham is under way.
- Felbridge, Copthorne Road08/02/2010Work on a £47,000 project to replace old gas mains in Felbridge, West Sussex, will begin shortly.
- Godalming, Church Street21/07/2010We are currently carrying out work on a project to renew the gas main network in Godalming.
- Godalming, Ockford Road17/03/2009A £390,000 project to renew gas mains in the Ockford Road area of Godalming begins on 30 March.
- Gravesend, Singlewell Road and Old Road East03/08/2010We are currently carrying out work on a project to renew the gas main network in Gravesend.
- Guildford, Friary Street area21/07/2010We are currently carrying out work on a £170,000 project to renew the gas main network in Guildford town centre.
- Hampton, Percy Road area07/10/2009Work is progressing on a £1.5 million project to upgrade the gas supply network in the Percy Road area of Hampton.
- Hawkhurst, Whites Lane14/07/2010We are currently carrying out work on a project to renew the gas main network in Hawkhurst
- Haywards Heath, Balcombe Road24/06/2010Work has begun on a project to renew the gas main network in Haywards Heath
- Kingston, Wood Street09/02/2010Work has begun on a project to renew and reinforce the gas supply network in Kingston.
- Leatherhead, Kingston Road11/08/2010We are carrying out a £900,000 project to renew gas mains in Leatherhead.
- London (Brixton), Coldharbour Lane area12/02/2010We are currently carrying out work on a £665,000 project to upgrade the gas supply network in Brixton.
- London (Greenwich), Greenwich Church Street18/08/2010We will shortly be working on a £172,000 project to renew gas mains in Greenwich
- London (Greenwich), Westcombe Hill15/01/2010We are carrying out a £216,000 project to renew gas mains in Westcombe Hill, Greenwich
- London (Streatham), Leigham Court Road area22/07/2010We are currently carrying out essential work on an £800,000 project to renew the gas main network in Streatham.
- London (Streatham), Mitcham Lane21/05/2010We will shortly be carrying out essential work on a project to renew the gas main network in Streatham.
- London SE1, Bermondsey Street15/02/2010Work on a £150,000 project to replace gas mains and services in Bermondsey will get underway soon.
- London SE1, Borough High Street23/02/2010Work is progressing on a £637,000 project to replace 1.3 kilometres of ageing gas mains and services in Borough High Street.
- London SE13 (Lewisham), Lewis Grove03/08/2010We will shortly be carrying out essential work on a £93,000 project to renew the gas main network in Lewisham.
- London SE23 (Forest Hill), Waldram Crescent10/08/2010We will shortly be carrying out a £261,000 project to renew gas mains in Forest Hill.
- London SE26 (Sydenham), Sydenham Road12/05/2010We are in the final phase of a £2million project to renew the gas main network in Sydenham
- London SM1 (Sutton), High Street18/02/2010Work is progressing on a £270,000 project to upgrade the gas main network in Sutton.
- London SW11 (Clapham), Grant Road area03/08/2010We will shortly be carrying out essential work on a project to renew the gas main network in Clapham.
- London SW12, Balham High Road21/05/2010Work is progressing on a project to renew the gas main network in Balham
- London SW15, Upper Richmond Road01/07/2010We will shortly be carrying out work on Phase 2 of a project to renew the gas main network in London SW15.
- London SW17 (Tooting), Mellison Road01/07/2010Work to renew the gas main network in Tooting is underway.
- London SW18 (Wandsworth), Trinity Road16/07/2010Work is underway on a project to renew the gas main network in Wandsworth.
- London SW18, North Side Wandsworth Common17/03/2010We are nearing completion on a project to renew the gas main network in Wandsworth.
- London SW19, Merton High Street08/12/2009Work is progressing on a £500,000 project to upgrade the gas supply network in Merton
- Mereworth, Malling Road29/06/2010We will shortly be carrying out work on a £160,000 project to renew the gas main network in Mereworth.
- Penge, High Street03/08/2010We are currently carrying out work on a £250,000 project to renew the gas main network in Penge.
- Poole, Ashley Road area07/06/2010We will shortly begin carrying out work on a £1.3million project to renew the gas main network in the Ashley Road area of Poole.
- Purley, Brighton Road10/08/2010We are carrying out a £350,000 project to renew 1.4km of gas mains in Brighton Road, Purley.
- Ramsgate, Allenby Road & Margate Road18/01/2010We will shortly be starting a £750,000 project to renew gas mains in the Allenby Road and Margate Road areas of Ramsgate
- Reading, London Road at Cemetery Junction01/07/2010We are currently carrying out work on a £500,000 project to renew the gas main network in Reading.
- Richmond, Lower Teddington Road21/05/2010We will shortly be carrying out essential work on a project to renew the gas main network in Richmond.
- Rustington, The Street area04/01/2010Work is underway on a £650,000 project to renew and reinforce the gas main network in Rustington.
- Sandwich, Woodnesborough Road20/07/2010Work on a £375,000 project to renew the gas main network in Sandwich is underway.
- Sherborne, Newland05/01/2010Work will shortly be starting on a £366,000 project to renew the gas supply network in Sherborne.
- Sidcup, Station Road area28/05/2010Work on a £1million project to renew the gas main network in Sidcup is underway.
- Southampton, Archers Road and Hill Lane24/07/2009We are in the final work phase of a £1million project to replace aging gas mains in Archers Road and Hill Lane.
- Southampton, Bevois Valley Road07/06/2010A £468,000 project is currently taking place in the Bevois Valley Road area of Southampton
- Southampton, High Road07/06/2010We will shortly be working to replace gas mains in High Road, Southampton
- Southampton, Redhill07/06/2010Around 2.7km of old mains are being replaced as part of a £380,000 project in Redhill, Southampton
- Southampton, Romsey Road12/07/2010Work to renew the renew the gas main network in Southampton is underway.
- Southampton, Shirley Road and Millbrook Road East07/06/2010We are renewing 2km of gas pipes in a £366,000 project in Shirley Road and Millbrook Road East, Southampton
- Southampton, St Aubins Avenue07/06/2010We are investing £350,000 to replace more than 2km of mains in the St Aubins Avenue area of Southampton
- Speldhurst29/06/2010We have begun carrying out work on a £160,000 project to renew the gas main network in Speldhurst.
- St Leonards, Bohemia Road03/09/2009A £300,000 project to replace 900 metres of gas main in St Leonards gets underway on 21 September.
- Stone, Oxford Road06/08/2010Work on the final phase of a £500,000 project to renew the gas main network in Stone will get underway shortly.
- Sundridge, Main Road08/02/2010We will shortly be carrying out work on a £140,000 project to renew and reinforce the gas main network in Sundridge.
- Sutton, Whitby Road03/08/2010We will shortly be carrying out essential work on a project to renew the gas main network in Sutton.
- Tunbridge Wells, Eridge Road23/07/2010We are carrying out a £118,000 project to replace old, metal gas mains in Eridge Road, Tunbridge Wells.
- Tunbridge Wells, Sandhurst Road29/06/2010We will shortly be carrying out work on a £180,000 project to renew the gas main network in Tunbridge Wells.
- West Byfleet, Old Woking Road11/02/2010We will shortly be starting work on a £1.2 million project to renew and reinforce the gas main network in West Byfleet.
- Wokingham, Nine Mile Ride area02/03/2010We will shortly begin carrying out work on a £1.25 million project to renew the gas supply network in the Finchamstead area of Wokingham.
- Woodley, Headley Road area04/05/2010We are currentling carrying out work on a £2.2 million project to renew the gas main network in Woodley.
- Worthing, Brighton Road area20/10/2009A £1m project to replace ageing metal gas mains and services in Worthing is now underway