    Our work is progressing well. We have excavated at the locations of the existing gas mains pipes in both the High Street and St John Street. 

    To help prepare for our new mains connection we have excavated a hole in the High Street approximately 30m x 2m x 2m. We’ve also excavated a track in Blackfriars Street, from the junction with the High Street to the junction with New Skinners Close. 

    We’ll now be focused on laying our new large diameter pipe in these locations.

    Our teams continue to work seven days a week.

    We'll be updating our website as the project progresses. 

      The gas main excavation in the High Street