• Edinburgh Old Town

     

    Project update: Tuesday 18 July 

    Our work in the Holyrood Road area is continuing.

    Holyrood Road is temporarily open between Viewcraig Gardens and St John Street.

    There are temporary traffic lights currently in place at the Pleasance junction. These will be removed before rush hour on Thursday morning, once the tar used to reinstate the road surface has hardened.

    Holyrood Road will then be fully closed again for up to six weeks, with diversions in place.

    Our work in the High Street (Phase 8 of the project) will not take place now until mid-September. When our work is completed there, we’ll be reinstating the cobbles/setts.

    We're sorry for any inconvenience caused by our work, and would like to thank local residents, businesses and road users for your continued patience.