• Bathgate
    Inchmuir Road

     

    Start date: 4 December 2017
    Approximate duration: 3 weeks

     

    As part of a wider roadworks project the council is carrying out in the town, we are working to upgrade the gas network in Inchmuir Road, Bathgate.  This will ensure a continued safe and reliable gas supply for homes and businesses now and long into the future. 

    In consultation with West Lothian Council, we will be working in Inchmuir Road, at its junction with Blackburn Road, from Monday 4 December. Our project will take approximately three weeks to complete, but will be finished before Christmas. We’ll be working five days a week, 8am – 4pm, and will work weekends and extended hours when required. 

    Due to the location of our main, we’ll need to implement three-way temporary traffic lights at the junction to ensure everyone’s safety.

    The lights will be manually controlled during peak travel times to reduce disruption for motorists as much as possible.