• Bearsden
    Carse View Drive 

     

    Start date: 16 October 2017
    Approximate duration: 17 weeks

     

    We’re investing £256,000 to upgrade our gas network in the Bearsden area of Glasgow.

    This essential work involves the replacement of old, metal gas mains with new plastic pipe to ensure a continued safe and reliable gas supply.

    Following discussions with East Dunbartonshire Council, the work will start on Monday 16 October 2017 and will last for approximately 17 weeks. We’re carrying out this project over three phases to reduce disruption as much as possible. 

    You’ll find further details, such as where we’ll be working, in our customer leaflet.