    Start date: 1 August 2017
    Approximate duration: 10 months

     

    We’re investing £970,000 to upgrade our gas network in the Clarkston Road area of Muirend.

    This essential work involves the replacement of old, metal gas mains with new plastic pipe to ensure a continued safe and reliable gas supply.

    Following discussions with Glasgow City Council, the work started in August 2017 and will last until May 2017.

    We initially planned to start our work late in September 2017. However, due to road resurfacing work by the council in Windlaw Gardens and Ormonde Avenue in August, we decided to start work early. This helped us to avoid digging the newly resurfaced road and causing further inconvenience to road users and residents.

    Our work began in Clarkston Road in August 2017. During our project, we’ll also be working in the following streets:

    • Bogton Avenue
    • Cairndow Avenue
    • Deanwood Avenue
    • Deanwood Road
    • Gavinton Street
    • Linn Dive
    • Muirend Road
    • Netherlee Road
    • Oakley Drive
    • Ormonde Avenue
    • Ormonde Court
    • Ormonde Crescent
    • Ormonde Drive
    • Parklands Road
    • Windlaw Gardens

     

    Further details on this project can be found in our project leaflet.