• Crieff
    Perth Road area


    Start date: 8 January 2018
    Approximate duration: 10 weeks


    As part of a wider £930,000 project in the area, we'll shortly begin work to upgrade our gas network in the A85 Perth Road area of Crieff. 

    This essential work involves the replacement of old, metal gas mains with new plastic pipe to ensure a continued safe and reliable gas supply.

    Following discussions with the local authority, the first section of this project will start in Perth Road on Monday 8 January and will last for approximately 10 weeks.

    Our project will begin in Perth Road at its junction with Callum’s Hill and will continue south-west along the road for 10 weeks until we reach its junction with Dollerie Terrace. Temporary traffic lights will be in place around our work area for the duration of this phase, and will move along the road as our work progresses. 

    To ensure continued traffic flow in Perth Road, we’ll be temporarily closing its junctions with Murray Lane and Rectory Road when our work reaches these points. 

    We'll also be working in Ochil View Gardens between its junctions with Perth Road and Hazel Avenue for approximately eight weeks.

    So we can complete this project as soon as possible, we'll have multiples teams working in the area. For the duration of our 10 week project, we’ll also be working in the following streets: 

    Ancaster Road:

    We’ll be working here from 22 January 2018 for approximately three weeks 

    Strathearn Terrace:

    Our work in this street will last for approximately four weeks. The road will be closed temporarily but access for residents will be maintained at all times. 

    Ferntower Road and Anthony Place:

     We’ll be working in these locations for approximately eight weeks in total. Ferntower Road will be closed between its junctions with Connaught Terrace and Victoria Terrace. Access for residents will be maintained at all times. 

    Connaught Terrace and Hope Place:

    The last section of our work will take place in Connaught Terrace and Hope Place and will last for approximately four weeks. 


    Once this section of our project is complete, we’ll be working in the King Street area, followed by the North Bridge Street area of Crieff.