    Riverside Drive

     

    Start date: 30 July 2018
    Approximate duration: six weeks

     

    Update October 2018:

    After further consultation with the local authorities, our work in Riverside Drive was postponed due to the building of the V&A Museum, to reduce disruption for motorists. 

    Our engineers returned to site on Monday 1 October to complete the work.

    All being well, we expect to have completed our work and have reinstated the road surface by Friday 19 October. The road will then be fully re-opened.

     

    We’ll shortly start work to upgrade the local gas network in Riverside Drive, Dundee, to help meet an increased gas demand from local homes and businesses.

    Following discussions with Dundee City Council, our project will start on Monday 30 July and last approximately six weeks. We’ve split the project into two phases to help minimise disruption

    During phase one of our work we’ll be working in Riverside Drive, near the entrance for Barnetts Mazda garage. To ensure everyone’s safety while we work, two-way temporary traffic lights will be in place around our work area. We expect this phase to be complete within three weeks.

    Our work will then continue eastwards along the road. During phase two we’ll be working east of Tay Rail Bridge and three-way temporary traffic lights will be in place around our work area. Riverside Approach will also be closed to southbound traffic and a diversion route will be in place for motorists.