• Chipping Norton, Oxfordshire
    Burford Road

     

    Start date: 27 November 2017
    Approximate duration: Six weeks

     

    As part of a project to ensure a continued safe and reliable gas supply to the local community, the existing metal gas mains in Burford Road need to be replaced with modern plastic pipe.

    The essential work forms part of a mains replacement programme developed with the Health and Safety Executive. Following discussions with Oxfordshire County Council, the project will start on 27 November for six weeks.

    To ensure the safety of our engineers and the public, Burford Road will be closed between its junctions with Walterbush Road and Albion Street. A signed diversion will be in place for all vehicles, although local access will be maintained for residents.

    The road closure will be lifted between Thursday 7 December and Monday 8 January for the Christmas embargo.