• East Grinstead (RH19)
    London Road

     

    Start date: Monday 9 October 2017
    Approximate duration: 12 weeks

     

    We are working to upgrade the gas supply network in London Road, East Grinstead.

    We are investing £74,000 to replace our old gas mains and services with new plastic pipe to ensure a continued safe and reliable gas supply to the local area.

    In consultation with West Sussex County Council, we will be working in London Road in two phases.

    We’ll start our first phase on Monday 9 October. We need to temporarily close one lane in London Road (A22) between Station Road and St James Road. Traffic will be reduced to one lane around our work area for approximately five weeks.

    We’ll suspend our project on Friday 17 November until the new year to avoid disruption during the busy festive period.

    On Monday 8 January, we’ll start our second phase of work in London Road at its junction with Railway Approach. We’ll need to temporarily close London Road at this junction for seven weeks. A signed diversion will be in place.

    Further details on this project can be found in our project leaflet.

    We understand that people can get frustrated by roadworks. However, the new plastic pipe has a minimum lifespan of 80 years. This means that when the work is complete, East Grinstead homes and businesses will continue to enjoy the benefits of a safe and reliable gas supply for years to come.

    A map of where phase one of SGN's roadworks in East Grinstead will take place.One lane in London Road (A22) between Station Road and St James Road will be closed