Earley, Betchworth Avenue

We're upgrading our gas network pipes in and around Earley, Reading, replacing our old metal gas mains and services with new plastic pipes. This essential work will ensure your community continues to receive a safe and reliable gas supply.

Our contractor, I&G Contractors, will be completing this project on our behalf and will start work on Monday 4 December.

Our engineers will be working in the following roads:

 

Aldbourne Avenue and Ramsbury Drive

Monday 4 December to Thursday 29 February 2024

While we are working in Aldbourne Avenue and Ramsbury Drive, we will ask road users to ‘give and take’ past our work site for everyone's safety. We'll be closing the work site for Christmas before returning in early January.

 

Betchworth Avenue

Monday 4 March 2024 to Wednesday 15 May 2024

For the safety of everyone around our work site, we'll need to temporarily close Betchworth Avenue. Access will be maintained for residents and businesses and a signed diversion will be in place for road users.

 

Silverdale Road

Monday 4 March 2024 to Wednesday 15 May 2024

For the safety of everyone around our work site, we'll need to temporarily close Silverdale Road. Access will be maintained for residents and businesses and a signed diversion will be in place for road users.

 

Wilderness Road

Monday 15 April 2024 to Tuesday 21 May 2024

While working in Wilderness Road, we'll need to install temporary multi-way traffic signals to allow road users to safely pass our work site.

 

We understand people can get frustrated by roadworks and so we only use traffic management that we feel is efficient enough to complete these works safely for ourselves and the public.