Q&A community event
We're attending a West Chiltington Borough Council Q&A evening on Wednesday 9 December to give residents and businesses an opportunity to find out more about our essential work in the area.
Our teams and contracting partners will be on hand to answer any questions about the project, road closures, traffic management arrangements and how access will be maintained.
Venue: The Sports Pavilion, Mill Road, West Chiltington, RH20 2PZ
Time: 6.30pm
Upgrading our pipes in West Chiltington and Pulborough
Our gas infrastructure underpins homes, hospitals, schools and businesses across West Sussex. Much of it was built decades ago and, while it continues to operate safely today, some assets are reaching the end of their engineering life.
SGN is investing in new plastic pipes here to ensure a safe, reliable and resilient network for thousands of people who depend on it every day, while enabling the long-term transition to lower-carbon energy systems.
It will begin in January 2027 and be carried out in several phases to help minimise disruption to the local community. We expect the project to be completed in November 2027.
We recognise roadworks can be frustrating for residents, businesses and road users. Thank you in advance for your patience and understanding while we complete this essential work.
When we'll be working in your street
Phase one
- January to May
- Roads affected: West Chiltington Road, Harborough Hill, Monkmead Lane and Castlegate
- Road closures will be in place for everyone's safety
Phase two
- May to October
- Roads affected: Nyetimber Lane, Silver Wood, Nyetimber Copse, The Common and Little Hill
- Road closures will be in place on several sections of the route
- Temporary two-way traffic lights will be installed on Silver Wood
- Give-and-take traffic management will be in operation on Nyetimber Copse
Phase three
- September to November
- We'll be working in Foxfields
- Localised carriageway restrictions will be in place during this final phase
What do the closures mean for me?
- Signed diversions will be in place for affected motorists.
- Vehicle access for residents will be maintained from one end of the closure. Our engineers and local signage will keep road users and residents informed.
- Parking bays will be suspended at times during our work. Signage will be installed in advance to notify of upcoming suspensions.
- Bus routes may be impacted. We advise residents to contact their service provider for the latest updates on changes to services/routes, timetables and bus stop locations.
- All businesses will remain open around our closure areas. Access to these commercial properties will be maintained throughout.
- We’ll work with the local council to ensure refuse collections can continue to be made with as little disruption as possible.
Why this project matters
Strengthening critical infrastructure
These upgrades will improve safety and reliability for the local community
Avoids short-notice disruption
Not investing in upgrades here risks unplanned gas outages, emergency repairs and greater long-term disruption
Delivering energy sustainably
Renewing our pipes will help cut methane emissions and support the transition to renewable gases such as biomethane