Levenmouth, H100 Fife hydrogen network

We’re progressing well with the construction of our world-first H100 Fife green hydrogen gas network in the Buckhaven and Denbeath areas of Levenmouth, Fife.


H100 Fife is leading the way in decarbonising home heating. It will be the first 100% hydrogen-to-homes zero carbon network anywhere in the world, demonstrating the potential for the whole British gas network to deliver hydrogen gas.

Using green hydrogen gas means no carbon will be produced when it’s burned, which is much better for the environment and puts us on a clear path towards net zero heating. It’s a historic change that will make Scotland and the UK a greener place to live – and it all starts here, in Buckhaven and Denbeath.

Our project started in May 2023 and will last 15 months. We’ll be carrying out our work over five phases as detailed below, to minimise disruption to the local community as much as possible. The dates provided are subject to change.

During each phase of our work, it may be necessary to implement road closures and use temporary traffic lights at times. We’ll give as much advanced notice of this as possible.

You can see a map below of the streets we'll be working in during each phase and a schedule of dates for these phases.

Media library image
A map showing where we'll be working during our project to construct a new hydrogen network in Levenmouth.


Phase one, two and three are now complete and phase four is underway.

 

Phase four: We're working in the following streets at different times between February 2024 - April 2024.

  • Sandwell Street - COMPLETE
  • Ruskin Crescent - COMPLETE
  • Stark Street - COMPLETE
  • Den Walk - Work is ongoing and expected to be complete on 13 June 2024

Phase five: We'll be working in the following streets at different times between April 2024 - August 2024.

  • Buchan Gardens - Work starts 15 July 2024 until 2 August 2024
  • Burns Avenue - Work starts 1 July 2024 until 22 July 2024
  • Carlyle Crescent - Work starts 17 June 2024 until 12 July 2024
  • Den Walk - Work starts 6 May 2024 until 14 June 2024
  • Omar Crescent - Work starts 3 June 2024 until 28 June 2024
  • Shakespeare Avenue - Work starts 17 June 2024 until 12 July 2024
  • Wellesley Road - Work is ongoing and expected to be complete on 6 June 2024