From Monday 11 August our specialist contractor, WCB, will be working to upgrade the gas network in the Woodhyrst Gardens area of Kenley. Work will be ongoing for approximately four weeks.
The project involves us replacing the old, metal pipes with new longer longer-lasting plastic ones to ensure local homes and businesses continue to receive a reliable gas supply.
The work involves:
- From 11 August for 4 weeks, our engineers will be working in the Woodhyrst Gardens area, along the whole length of Beckett Avenue
- From 11 August for 3.5 weeks, engineers will also be working along Foxley Road, from the junction with Park Road to Beckett Avenue
Road closures will be in place along Beckett Avenue and Foxley Road, respectively.
Maintaining access
Whilst work is ongoing, we will ensure:
- Pedestrian access and property access is maintained
- Local businesses and residents continue to receive deliveries. We ask that people speak to our site team regarding any specific access arrangements
- Emergency access will be maintained
We appreciate how disruptive traffic management is for residents and road users, and assure you that our engineers are committed to doing everything they can to complete these works as quickly and as safely as possible.
If you have any specific questions regarding these works, please email customer@sgn.co.uk.
We’re sorry for the inconvenience this work will cause, and thank local people for their patience and understanding.